News GST

  • Sep 22, 2018
  • State appellate body upholds GST on liquidated damages

    In a ruling that may have an impact on several construction and renovation contracts and contract cancellations, Maharashtra Appellate Authority for Advance Rulings (AAAR) has upheld a levy of GST on liquidated damages collected by a power generation firm for a delay in project completion. Liquidated damages are fines levied by the owner of a project to the contractor in case of cancellation or delay of trial operation within the specified time period in the contract.